Virtual Pharma Company, Large Pharma - IMP Supply Project and fast track clinical trial supply case studies.
Client: Virtual Pharma Company
Challenge:
- Problematic formulation and analytical method
- Blinding issues with market leading comparator
Penn solution/ongoing support:
- Developed a suitable manufacturing process and re-built the analytical method
- Over-encapsulated market leading comparator and developed the analytical method to general appropriate stability data
- Support for three simultaneous phase III trials
- Average of 1,800 patients per trial
- Multi national trial – EU, US and ROW
- 64,000 monthly kits over two years
- Bespoke child resistant – senior friendly (CRSF) packaging solution
- Liaise with two CROs
- Liaise with two IVRS providers
- Penn arranged multiple global distribution depots
Client: Large Pharma – IMP Supply Project
Challenge:
- Each patient pack contained four products – 16 vials
- Multinational trial – US, EU and ROW
- Supplies despatched at 2°C-8°C to countries with varying external ambient temperatures
Penn solution/ongoing support:
- Bespoke packaging configuration
- Multiple global distribution depots
- Use of specialist courier
- Use of PDF data logger with programmable alarm
Fast track CTS case studies
Phase I dose escalation
- Dose escalation study required extra cohort of 16 patients urgently to complete study
- Monday: Teleconference with client
- Tuesday: Prepare and approve documents for label text
- Wednesday: Product labels, receive product from manufacturer
- Thursday: Pack, release and distribute product
Phase I toxic compound
- Required 20 patient kits packed and shipped at -20°C – highly toxic compound
- Product could only remain out of freezer for maximum of five minutes
- IMP packed by team in walk-in freezer
- Classified as dangerous goods i.e. special pack and shipping conditions
- Shipped successfully to site in Estonia on time
Blinded complex study
- Nine drug materials, seven table strengths + active and placebo auto-injectors
- Innovative approach to labelling to ensure injector remained blinded after firing
- Tables shipped refrigerated due to stability issues
- Short timescales
- Project completed successfully and on time